Contribute to shorten shutdown time by our cooling solution at World’s largest refinery.

Place: Gujarat.

Company’s profile: Client is a leading petrochemical and refinery brand owning businesses across India indulged with other fields like energy, textiles, natural resources, retail, and telecommunications also.

They have a private sector crude oil refinery in Gujarat. The refinery was commissioned in the year of 1999 dated 14th July, and is currently the largest refinery in the world.

Situation:

The Domestic Tariff Area (DTA), the cooling time in the maintenance cycle was high which is ideally required to be lower for better productivity.

Solution offered:

Studying the process our experts initially offered with Chiller and AHU combination to cool the gasifier to the ambient temperature with reduced time teamed up under our solution category for Rapid cooling.

Later on, the experts suggested to customize and tailor needs of cooling by inculcating portable air conditioners for improved performance and eased mobility.

Benefits:

Productivity increased, with less time taken by the reactor for cooling the time for performance and deliverance increased.

Why they chose us?

  • Readily available technology and help.
  • Tailored and customized equipment.
  • Fast installation with eased mobility.
  • Improved and individualistic service support.

Solutions

Process Cooling

Cooling solutions to remove heat from a process. Helps maintaining a constant fluid temperature and flow regardless of the load to continue process with desire production.

Bridge Cooling

Cost-effective, additional cooling to cope up critical needs such as seasonal heat waves and business peaks. Bridge cooling lets you conserve capital instead of purchasing equipment used only at certain times of the year.

Rapid cooling

An essential service requirement during shutdown and planned maintenance to make equipment available for maintenance operating at very high temperature to reduce unproductive time during shut down.

Emergency requirement

Helping to cope up emergency cooling and/or power requirement during a breakdown, grid conflict, natural calamities, fire incidences or any accidents resulting in non-availability of cooling and/or power generating equipment. A must solution to restore such services in a short span of time for a temporary period.

Planned Shutdown requirement

A well-planned and thoroughly investigated solution that avoids disruptions in providing cooling and/or power due to facility shutdowns for maintenance, renovation, etc. A safe, mobile & modular and plug and play featured equipment helps you to continue with production during a planned shutdown of such utilities.

Trial & Test for safe investment

All trials and errors prechecked before installing the unit into the facility in order to avoid the hindrance of post-installation complaints, services, and hassles.